Handle a component shortage with a dated shortage register, a qualified alternate path and explicit purchasing authority. The right action depends on the affected part and build. A candidate that fits the footprint, an online stock listing and a customer-approved replacement are three different things.
If you want one supplier to source the parts and build the boards, see turnkey PCB assembly in China.
1. Establish what is actually short
Start with the released BOM and order quantity. Record the exact manufacturer part number, quantity per board, fitted variant, required quantity, accepted on-hand stock and confirmed inbound supply. Identify the date by which material must be available for the planned operation.
On small screens, scroll the table sideways to compare columns.
| Field | Record | Why it changes the decision |
|---|---|---|
| Part and demand | MPN, BOM revision, quantity and required date | Prevents a quote or alternate being applied to the wrong build |
| Supply records | Seller, source date, available quantity and order confirmation | Separates an indication from an actual supply commitment |
| Alternate status | Candidate, under evaluation, approved or restricted | Defines whether purchasing and production are authorized |
| Schedule impact | Affected operation and earliest validated recovery date | Shows whether the proposed action changes the critical path |
| Decision responsibility | Engineering approver, buyer, scope and expiry | Prevents an emergency decision becoming an uncontrolled default |
Check ordering multiples, minimum quantities, delivery terms and the validity of the offer. Do not count quarantined, unapproved or already allocated stock as freely available to the build.
2. Define what AVL approval means
Organizations use AVL, approved manufacturer list and approved-parts list differently. State whether your register approves a manufacturer part number, a seller or both. Approval of a distributor does not establish that every proposed component is a qualified replacement.
For an alternate part, evaluate the requirements that matter to the design: pinout, package, electrical limits, temperature range, timing, firmware interaction, marking, assembly process and any applicable product qualification. Record the records and remaining tests. “Same value and package” is not enough to establish interchangeability.
Keep a temporary deviation limited to its approved quantity, lot, variant or period. A permanent BOM change follows the released change process. The alternate-part qualification guide covers the detailed evaluation and release records.
3. Verify source and lifecycle information
Use the component manufacturer's current authorized-channel information when selecting a source. For example, Texas Instruments recommends buying directly or through its authorized network and describes limitations for parts purchased elsewhere. Apply the policy of the actual manufacturer and the project's approved sourcing rules; a generic visual inspection does not establish authenticity.
Keep the original product-change or discontinuance notice with the affected MPNs, dates and decision. TI's PCN guidance identifies information such as affected products, qualification records and implementation or last-order dates. Use the actual notice rather than assuming every manufacturer or event follows the same timetable.
4. Compare recovery paths against the deadline
- Wait for the original part: validate the supply commitment and its effect on the build plan.
- Qualify an alternate: include engineering, sample procurement, firmware or fixture changes and validation time.
- Authorize a partial build: define which units or operations may proceed and how unfinished work will be identified, stored and retested.
- Redesign: account for new PCB, BOM, software and validation releases before treating it as a schedule solution.
Compare these paths with the lead-time dependency example. Buying a part sooner helps only if the approved material becomes available in time to change the controlling milestone.
5. Calculate buffer demand with explicit assumptions
Hypothetical inventory example: a planning horizon requires 600 boards, with two devices per board. Base demand is 1,200 devices. Engineering and procurement agree a 5% planning allowance for this example, producing a target of 1,260. There are 300 accepted, unallocated devices on hand and 200 confirmed to arrive before they are needed. The additional requirement is 1,260 − 300 − 200 = 760 devices, before order multiples and minimum purchase quantities are applied.
The 5% figure is illustrative; it is not a recommended scrap rate or universal safety-stock policy. Set the allowance and planning horizon from demand uncertainty, consumption history, replenishment risk and storage constraints. If the 200 inbound devices cannot arrive in time, the usable supply changes and the calculation must be reopened.
Agree who owns excess stock, whether an order is cancellable, the permitted spend, storage requirements and review dates. A forecast informs planning; it does not by itself authorize an irreversible material purchase.
6. Close the shortage decision into the build record
Link the approved MPN, seller, material lot, deviation or change number, affected boards and required test configuration. Update receiving and production instructions before the material is issued. Retain the original requirement and the approved change so repeat orders do not inherit an emergency substitution silently.
Use the lifecycle-alert workflow for ongoing notice review. For a quotation, provide the BOM, quantity, required date and no-substitute lines through the PCBA RFQ form.
Common shortage questions
Can a supplier select an equivalent part automatically?
Only within authority explicitly granted for that part and build. State the approval scope and required records before purchasing.
Does buffer stock remove supply risk?
No. It can cover defined demand exposure, but storage, obsolescence, forecast changes and allocation still require review.