A passing prototype is not a complete production-release record. After a pilot build, connect each open issue to the affected configuration, an approved rework or scrap decision and records that the proposed action was checked. This guide addresses the decision after pilot results are available. For the earlier development stages, use the EVT, DVT and PVT handover guide.
Define which configuration is being released
List the PCB, BOM, placement, drawing, firmware, fixture and test-procedure revisions used in the pilot. Compare them with the proposed production package. If they differ, identify the difference and its verification plan; do not let a pilot result silently approve a later configuration.
Record the tested quantity, any excluded units and the conditions of the evaluation. Keep first-pass results separate from results after retest or repair. A final pass count alone cannot explain whether a fixture problem, assembly issue or configuration change occurred.
Use an issue-closure register
| Field | What the release review needs |
|---|---|
| Issue and scope | Observed symptom, affected serials/lots, discovery point and relevant configuration. |
| Records | Original observation, measurement or log; the method and conditions used to obtain it. |
| Rework or scrap decision | Hold, approved repair, configuration change or another explicitly approved action; identify its scope. |
| Verification | How the action was checked, which units were evaluated and where results are recorded. |
| Responsibility | Responsible action owner and the function authorized to approve the technical and quality rework or scrap decision. |
| Release decision | Closed, conditionally accepted or still open, with the approval reference and any lot restriction. |
Illustrative example: a retest does not erase a failure
Suppose one pilot board fails a connector check, then passes after it is reseated in a fixture. This example is hypothetical. Keep the first failure, fixture identification, intervention and retest result in the record. Passing after reseating does not establish whether the cause was a board connection, fixture contact or test setup.
Assign a check that distinguishes those explanations, document the result and decide whether other pilot units or future lots are affected. The SMT defect investigation guide helps separate an observed condition from an assumed cause. For an intermittent result, also review the fixture handover requirements.
Check the controls that will change at volume
Review material source, approved alternates, panel arrangement, setup instructions, staffing assumptions, test sequence and packaging. Identify which proposed changes require a new first article or other verification under the agreed process. Pilot approval should state which configuration and conditions it covers.
For repeats, review the ICT fixture capacity and maintenance plan against the proposed schedule. Capacity is a planning assumption until the relevant resources and scope are confirmed.
Make the release decision explicit
Collect the configuration comparison, issue register, agreed acceptance criteria, first-article records and required delivery records. Record the decision, approver and affected build or lot. If an issue remains open, state whether it blocks release or is covered by a specific, approved exception. Do not label the whole program “production ready” based on an undocumented verbal agreement.
The first-article inspection checklist covers the unit-to-package review. The prototype-to-production readiness guide supplies the broader readiness worksheet. Use those records as inputs to the release decision rather than creating conflicting parallel approvals.
Reopen the review when its assumptions change
A new material, board revision, firmware image, fixture or process condition may affect the basis of approval. Route the change through the agreed change process, identify the verification needed and retain the connection to the earlier release. A successful pilot is records for the conditions actually reviewed; it is not unlimited approval for later variants.
Close implementation work before reusing a pilot approval
An agreed corrective-action proposal and a released implementation are different states. The handover register should identify which files, tools, programs and instructions changed, the records that verifies the change and the configuration authorized for repeat production.
On small screens, scroll the table sideways to compare columns.
| State | Records available | What remains before closure |
|---|---|---|
| Finding recorded | Observed condition and affected population | Cause/impact assessment and owned next action |
| Response approved | Authorized design/process proposal | Implementation in the tracked package |
| Implementation completed | Actual revised files/tools/instructions | Required verification and review |
| Closed for a defined scope | Accepted implementation and verification references | Reassessment if the covered assumptions change |
Hypothetical pilot gap: engineering approves a fixture-contact change, but the repeat order is scheduled with the earlier fixture revision. The finding is not implemented in that route merely because an approval email exists. Identify the actual fixture, complete the required verification and record the effective work-order boundary.
Review differences between the pilot and intended volume route, including people, tooling, material, handling, test capacity and records. State which differences need further records rather than relying on the pilot label. Use the stage-gate register and NPI checklist to connect open work with the activity it blocks.